Tata Power Renewable Energy Ltd (TPREL), a subsidiary of Tata Power, has commissioned a 100.8 MW wind power project at Ausa in Latur district, Maharashtra. The project will supply renewable electricity to Tata Power Mumbai Distribution and is expected to generate approximately 308 million units (MU) of power annually, supporting the company’s efforts to expand clean energy supply.
The project comprises 28 Horizontal Axis Wind Turbine Generators (WTGs), based on the SG 3.6-145 model. With its annual generation potential, the facility is expected to help avoid nearly 252,560 tonnes of carbon dioxide emissions every year, contributing to lower-carbon power generation.
During execution, the project encountered a major grid connectivity change, with the Extra High Voltage (EHV) line configuration revised from an underground cable system to a monopole arrangement. The modification required changes in design, procurement and on-ground execution. It also marked the first monopole installation undertaken by TPREL’s Wind Project Execution Division. Despite these additional complexities, the revised configuration was incorporated without affecting the overall project schedule.
Following the commissioning, TPREL’s total renewable utility capacity has increased to 12.1 GW. Of this, 7.3 GW is operational, comprising 5.9 GW of solar and 1.4 GW of wind capacity, while the remaining 4.8 GW is at various stages of implementation.