BMRCL to operationalise Mysore Road-Kengeri stretch in June 2021

The Bangalore Metro Rail Corporation (BMRCL) is planning to operationalise Reach-2 extension line, the 7.53 km Mysore Road to Kengeri stretch in June 2021. The Reach-2 extension line has six stations: Nayandahalli, Rajarajeshwari Nagar, Jnanabharathi, Pattanagere, Kengeri Bus Terminal and Kengeri. The civil and system works are nearing completion for station building and viaduct. Parking facility is provided at Nayandahalli, Rajarajeshwari Nagar, Jnanabharathi and two-level parking at Kengeri Bus Terminal. Traction and signalling works are nearing completion and after integration and migration of signalling systems from the existing section to the new section, train testing commenced from April 2021.